E & W Main Street Milling and Paving Sept 4-10

 
E/W Main St Milling & Paving Schedule 09/04/18 – 09/10/18


 

Milling

09/04 0700-1700 Milling: W. Main St. between S. Prospect Ave. & Portland Ave.

DETOUR ROUTE

E/B traffic West Church St. to S/B N. Washington Ave to E/B East Main St.

W/B traffic S/B N. Washington Ave. to W/B West Clinton Ave.

 

09/05 0700-1700 Milling: W/E Main St. between Portland Ave. & Hudson St.

DETOUR ROUTE

E/B traffic from West Main to N Front St., E/B West Church St., North Washington, E/B Hickory Ave

W/B traffic from Tenafly to East Clinton Ave. to West Clinton Ave. to N/B Prospect Ave.

 

09/06 0700-1700 Milling: E. Main St. between Hudson St. & Tenafly border.

DETOUR ROUTE

E/B traffic from West Main to North Washington, E/B Hickory Ave

W/B traffic from Tenafly to E. Clinton Ave to N/B Washington Ave. to W/B West Main St.
 
 
E/W Main St Milling & Paving Schedule 09/04/18 – 09/10/18
 
Milling
09/04 0700-1700 Milling: W. Main St. between S. Prospect Ave. & Portland Ave.
09/05 0700-1700 Milling: W/E Main St. between Portland Ave. & Hudson St.
09/06 0700-1700 Milling: E. Main St. between Hudson St. & Tenafly border.
 
 
Paving
 
 

 
09/07 0700-1700 Paving: W/E Main St. between S. Prospect Ave. & S. Woodside Ave.
09/10 0700-1700 Paving: E. Main St. between S. Woodside Ave. & Tenafly border.
 
 
***Scheduled work dates are subject to change due to weather***
 

 
 